Following is the proposed and actual schedule for the completion of the EAC web project.

TaskProposed ScheduleActual Completion
Writing & Submitting ProspectusJan. 1 - 31, 1997Jan. 1 - Feb. 3, 1997
Task AnalysisJan. 27 - Feb. 7, 1997Feb. 10 - 19, 1997
StoryboardingFeb. 7 - 21, 1997Feb. 17 - 22, 1997
Expert ReviewFeb. 17 - 28, 1997Feb. 24 - 28, 1997
HTML DevelopmentMarch 1 - 31, 1997March 1 - 22, 1997
One-on-one EvaluationsApril 1 - 15, 1997March 24 -31, 1997
Small Group EvaluationApril 16 - 30, 1997April 12 - 22, 1997
Writing ThesisMay 1 - 24, 1997May 1 - June 7, 1997
Submitting Thesis for ReviewMay 26 - 31, 1997June 9, 1997
Revising ThesisJune 1 - 14, 1997June 20 - 28, 1997
Submitting Thesis for Final ApprovalJune 16 - 20, 1997June 30, 1997
Oral DefenseJune 23 - 27, 1997June 30, 1997