|
Measurement
Project Requirements
| Prerequisite: |
|
Your Measurement Project may
be initiated as soon as you have successfully completed
the necessary coursework. For option A, IP&T 652 is
the only prerequisite. For options B, C, or D, IP&T
653 is also required. |
| |
|
|
| Overview: |
|
The measurement project is designed to help the student
apply information acquired through coursework and reading
to actual measurement problems and settings. Additionally,
the project allows the student to assume at least some of
the responsibility for conduct of an actual measurement
project. The project report and comprehensive exam should
be written and submitted together as one document. Procedural
instruction for meeting the Measurement and Comprehensive
Exam requirements are described below.
STEP 1: Faculty Sponsor
STEP 2: Enroll for IP&T 657R
STEP 3: Prepare Your Project
STEP 4: Complete the Project
STEP 5: Project Options
STEP 6: The Written Report
STEP 7: Faculty Sponsor Evaluation and
Final Grade
STEP 8: Comprehensive Exam
Prospectus Approval Form
|
|
|
|
STEP
1:
Faculty Sponsor |
|
A student desiring to complete a Measurement project
must identify a suitable project in consultation with a
faculty member and obtain the consent of the faculty member
to serve as their sponsor for the project. In most instances,
a student will co-author the report with the faculty sponsor.
The sponsor may or may not be a member of the student's
committee.
|
|
|
|
STEP
2:
Enroll for IP&T 657R |
|
Enroll for three hours of IP&T 657R
credit the semester the work is to be completed.
|
|
|
|
STEP
3:
Prepare Your Project |
|
- Prepare a prospectus - Prepare a prospectus
describing the proposed measurement project and submit
a copy to the Department Chair, along with the Prospectus
Approval Form signed by the faculty sponsor (see page
6). The Prospectus and Approval Form must be submitted
to the Department Chair before the work is begun,
and no later than the second week of the semester in which
the work is to be completed.
NOTE: It is desirable that students define the primary
purpose or focal issue of their Measurement project during
the latter part of the semester prior to the semester
in which they will work on the project.
Students should retain a copy of the Prospectus Approval
Form in their own files.
- Must be a defensible effort - In some
instances a project will be the outgrowth of one of the
two measurement courses (IP&T 652 or 653), or an Internship.
When this is the case, steps should be taken to ensure
that the effort is defensible in terms of the three hours
credit awarded for the project. This is accomplished by
establishing, in writing, that the two activities are
going to be combined and by having the joint effort approved
by the faculty sponsor and the Department chair in
advance.
It is not permissible to be awarded course or Internship
credit and project credit for the same activity unless
the total time devoted to the activity is commensurate
with the total amount of credit being awarded and approved
by the faculty sponsor. Double credit is not permissible.
The measurement and Comprehensive Exam requirement may
be challenged by making a formal request in writing to
the Department Chair and by submitting a report of a suitable
measurement project written prior to entering the Instructional
Psychology & Technology program, along with supporting
documentation as described in Step 5. Such reports will
undergo the same faculty review as those which received
advance approval.
- Funding - The Instructional Psychology
& Technology Department does not provide direct financial
support for projects. However, the student's time and
expenses related to a project may be funded by a sponsoring
faculty member or agency. If a student is unable to find
a sponsor who is able to fund the project, the costs must
be borne by the student.
- Schedule - Successful completion of
a Measurement or Evaluation Project is a necessary step
in qualifying for doctoral candidacy; therefore, students
cannot begin formal work on a dissertation before the
requirement is met. However, informal work (reading, assembling
related research, pilot studies, etc.) is encouraged as
early as possible in the program.
|
|
|
|
STEP
4:
Complete the Project |
|
After obtaining approval of the prospectus, the student
may proceed with the measurement project under the supervision
of the faculty sponsor. The student will submit those documents
required by the faculty sponsor. The faculty sponsor will
provide the criteria for each required document.
When a member of the faculty agrees to serve as a sponsor
for a measurement project, that faculty member agrees to
provide the student individual consultation regarding the
project on a regular basis and to review the student's work
systematically. How the measurement project is accomplished
is left up to the discretion of the faculty sponsor. The
only stipulation is that the faculty sponsor agrees to review
whatever the student writes in connection with the project.
At the outset of the project, the faculty member and the
student should determine specifically what the sub-tasks
are going to be and agree on deadlines for completing each
sub-task. The schedule in the prospectus should reflect
these deadlines.
|
|
|
|
STEP
5:
Project Options |
|
The requirements for the Measurement Project can be fulfilled
by successfully completing one of the four options described
below.
Option A. Construct a new assessment
instrument or procedure
- The instrument or procedure to be developed can be selected
from any of the following categories:
- An achievement test (A test intended for one-time
use in a classroom setting is not acceptable. To be
acceptable, the test must be good enough to warrant
repeated use in assessing a reasonably stable domain
that includes intended outcomes beyond the recall level.)
- A performance test for assessing learners’ ability
to do some complex task that is valued in the workaday
world outside of school contexts (The resulting test
should include all displays, materials, equipment, and
instructions necessary for actually administering the
test.)
- A diagnostic test of learners’ understanding/misunderstanding
of the concepts, principles, rules, or procedures included
in some domain that is a prerequisite for successful
performance or further study in the subject.
- A scale, inventory, or other instrument assessing
one or more affective characteristics (attitudes, values,
interests, anxieties, locus of control, academic self-esteem,
etc.) related to some instructional experience or educational
issue.
- In addition to the instrument or procedures developed,
the following ancillary products must be included to fulfill
this option:
- The set of written specifications used to guide the
development of the instrument or procedure.
- Evidence of an adequate review of relevant research,
theory, or subject matter content.
- Evidence of formative tryout and revision including
item analysis data, reliability estimates, and at least
content evidence of validity.
- A User’s Manual including procedures for administering
the instrument or procedure, scoring procedures and
criteria, and guidelines for interpreting the resulting
scores.
Option B. Conduct a validation study
of an existing assessment instrument
- Prepare a written summary of any previously conducted
reliability and validation studies. Include an assessment
of the strengths and weaknesses of these studies, and
identify validity issues which have not been adequately
addressed.
- Design and conduct a study to collect additional evidence
of the degree to which scores obtained from the instrument
in question possess or lack validity. (Remember that establishing
validity is a cumulative, ongoing process and that no
single study is likely to provide conclusive answers to
all validity issues. The goal here is to make substantive
contribution to this ongoing process.)
Option C. Conduct a study focused
on a practical measurement need or problem faced by a test-user
- The study could include one of the following:
- A standard setting study to empirically determine
what cut-off scores should be used to make mastery-nonmastery,
pass-fail, or admit-deny kinds of classification decisions
based on test scores.
- A study to detect test items that may be biased (differential
item functioning) against some definable subgroup of
the examinee population.
- An equating study designed to equate scores from one
test with scores from a different, but similar measure
(e.g. as the ACT and the SAT).
- A norming study that will provide relevant and representative
norms for interpreting scores from a newly-created instrument
or updated norms for an existing instrument.
- Estimate the relative magnitude of different sources
of error in supervising teachers’ ratings of student
teachers.
- Some other similar problem or issue approved by your
project sponsor.
- Prepare a written report for the client which describes
the procedures used, presents the results, discusses the
limitations of the study, and offers specific recommendations
based on the results.
Option D. Conduct research on an unresolved
methodological issue
- Select some unresolved methodological issue related
to educational measurement and conduct a research study
designed to help resolve this issue. Some possible problems
or issues include--
- Factors influencing the reliability of scores obtained
from performance tests
- The cost-effectiveness and feasibility of using “authentic”
tests
- Problems associated with the use of partial-credit
scoring
- Problems of using formula scoring with multiple-choice
tests
- Problems of using complex multiple-choice (Type K)
items
- Effects of using different approaches to standard
setting
- Effects of violating unidimensionality in applications
of item response theory
- Effects of ‘fat’ versus ‘slim’
matching in Mantel-Haenszel studies of differential
item functioning
- Problems associated with the use of technology in
assessing student knowledge or performance
- Prepare a report that defines the purpose of the study,
summarizes relevant previous research, describes the method
used, presents the results, and interprets the findings
in light of previous research and present practice and
theory. The report should be suitable for submission to
one of the following journals or an equivalent:
- Journal of Educational Measurement
- Applied Measurement in Education
- Applied Psychological Measurement
- Educational and Psychological Measurement
|
|
|
|
Step
6:
The Written Report |
|
Regardless of which option is selected, a written report
must be prepared. This document should include at least
the following information:
- The purpose of the project and the problem, questions,
hypotheses, or issues it was designed to address.
- A rationale or justification explaining the need the
study was intended to fill or the reasons why it needed
to be done.
- A critical, integrative review of relevant research
literature.
- The method used to collect data including a description
of the design, sample, instrumentation, and procedures
used.
- The results of the study including any products created
and statistical findings.
- Conclusions or recommendations accompanied by a discussion
of the implications of the findings for instructional
or measurement theory and practice.
- A critique specifying the strengths and weaknesses of
the study in light of existing theory in the field and
describing what you learned from the experience and how
you would improve the project if you were to do it again.
- The proposed schedule submitted with the prospectus,
an actual schedule describing how the study was actually
conducted, and an explanation for any discrepancies between
the proposed and actual schedule.
- A project budget comparing expenditures and actual expenditures
plus an explanation of discrepancies.
If you choose option A, a copy of all instruments and ancillary
products should be included as appendices to your report.
Data summarizing the results of tryouts and revisions should
be included either as tables in the body of the report or
in the appendices.
If you choose option C or D, the report you prepared in
Step 5 will substitute for items 1-6 in the above list,
but must be accompanied by a written critique incorporating
items 7-9 from the above list.
In preparing your measurement project report, you should carefully follow the style guidelines outlined in the Publication Manual of the American Psychological Association. You should consult the APA Guidelines web site prepared by the IP&T Department that outlines some of the ways to avoid the most common errors found in student papers and enumerates some variations from the guidelines recommended for dissertations and other student papers. You should also access the Microsoft Word Heading Styles Tutorial on how to use styles in Microsoft Word to facilitate the implementation of the APA heading guidelines. This tutorial includes a link to a Microsoft Word template document that includes all the necessary styles already defined. |
|
|
|
STEP
7:
Faculty Sponsor Evaluation and Final Grade |
|
When the faculty sponsor is satisfied the student has
demonstrated sufficient originality and quality in the report,
he will sign the attached evaluation report (see page 7)
verifying the student has satisfied the Measurement project
requirements.
The student will then submit two copies of the final project,
along with the faculty sponsor evaluation report to the
Department Secretary. The Department Secretary will then
send the project out to two additional readers for review
(see Step 8). The student will receive a final grade for
the project after the project passes these two readers.
The sponsor and readers will each grade the project, the
final grade will be an average of the three grades received.
The grade will not be submitted to the Records Office until
this Comprehensive Exam has been passed.
|
|
|
|
STEP
8:
Comprehensive Exam |
|
The completed project documents will be submitted by
the Department Secretary to two additional IP&T faculty
members for their evaluation. The reviewers should judge
the quality of the project and Comprehensive Exam in terms
of the criteria listed on the Faculty Evaluation Report
form (see page 7). (Note that these reviewers are not required
to judge the originality of the work, or determine if the
project requirements have been met. This is the responsibility
of the sponsor. However, they are required to review the
quality of all aspects of the project as outlined on the
Faculty Evaluation form.) The results of these evaluations
will be submitted on the Evaluation of Examination Form
(56) to the Department Chair. |
|
|
|
| Prospectus
Approval Form: |
|
The Measurement Project Prospectus Approval Form can
be downloaded here:
Word
Format (.doc)
|
|